Central Gas Facility Standby Generator Controls - Programming for controls upgrade on standby generator system for BP Central Gas Facility at Prudhoe Bay, Alaska. Project was executed with Marsh Creek, LLC and consisted of a control system and switchgear replacement for three 3.0 Megawatt diesel locomotive engines. Pat Rinehart performed ladder logic programming on Allen-Bradley ControlLogix programmable controllers and assisted with on-site commissioning. BP Central Gas Facility and associated Central Compressor Plant comprise the world's largest gas compressor complex.
Pipe Slotting Machine
Control System - Provided control
system for pipe slotting machines. Project was
executed in concert with Unique
Machine and Dowland-Bach
Corporation and consisted of control system and
control panel design for custom-built automated pipe
slotting machines. Project is currently in the
implementation stage, with multiple units slated for
production.